The 10-Business-Day Permit Shot Clock: How It Works and How to Enforce It

One of the most powerful — and least understood — parts of HB 803 is the permit "shot clock." It puts a hard deadline on the building department, and if they miss it, your permit is deemed approved. Here's exactly how it works and how to hold a jurisdiction to it.

What the shot clock says

Under HB 803 (effective July 1, 2026), when you use a qualifying private provider, the building department has 10 business days to review the plans or issue the permit — down from the prior 20-business-day standard. For minor single-trade residential work, the window is even shorter at 5 business days. If the department misses the deadline, the application is deemed approved.

Why this is a big deal

Permit delays are one of the biggest hidden costs in construction — carrying costs, financing, idle crews, and blown schedules. The shot clock flips the leverage: instead of waiting indefinitely on an overloaded department, you have a firm deadline with real teeth behind it.

How to actually enforce it

The private provider advantage

The shot clock only applies when a private provider is involved — it's one more reason the private provider route now beats the traditional path on timeline. Combined with same-day inspections and the HB 803 fee reductions, it turns permitting from an open-ended wait into a predictable, plannable step.

Tew & Taylor handles private provider plan review and inspections statewide and helps clients hold jurisdictions to the new timelines. See how the shot clock applies to your project.

Keep Your Florida Project Moving

Tew & Taylor provides private inspections, plan review, and permitting support across Florida under F.S. §553.791.

Get Started →